Farringdon Station revamp on track for December

PUBLISHED: 15:04 23 September 2011

Project director Richard Walker surveys Farringdon Station from the top of the new ticket hall

Project director Richard Walker surveys Farringdon Station from the top of the new ticket hall

Archant

A key stage of the Farringdon Station project which will lead to an increase in passengers is on track to be completed in December.

Twelve-car Thameslink trains wil run through Farringdon Station from Monday, December 12, once two platforms have been extended. At present Thameslink, which provides services between Bedford and Brighton, operates four and eight-car carriages.

In December, a new large glass-roofed ticket hall for Thameslink and, in the future, CrossRail travellers opens opposite the London Underground entrance.

The technical platform extension work is being carried out underneath Cowcross Street as thousands of comutters pass above everyday.

The construction is complex because it is being undertaken around the 1920s main entrance building which is protected with Grade II-listed status.

Background on Farringdon Station project

- The Farringdon redevelopment is part of the wider £6 billion Thameslink Programme delivered by Network Rail.

Blackfriars and London Bridge stations are also being revamped. By 2018 Thameslink will run a metro service between Bedford and Brighton with 24 trains every hour.

- At the same time CrossRail services will pass through Faringdon. CrossRail, which runs trains underground between Paddington and Liverpool St, has now started construction in Farringdon Road on the site of the old Cardinal Building. When CrossRail and Thameslink services meet at Farringdon in 2018, passengers will be able to travel to Heathrow, Gatwick, Luton and City airports along with St Pancras International for Eurostar.

Richard Walker, Network Rail project director, said: “This is major level engineering on an old building in a constrained environment next to a very busy live railway and essentially nobody knows what we are doing.

“We have maintained all the Grade II-listed fabric. It will look fantastic.”

Farringdon Station is closed at weekends but remains open during the week.

Since the construction began in 2008 15 Thameslink trains stop every hour up from eight and two new staircases have opened on platform one and two.

Mr Walker said: “We have almost doubled the frequency of passenger services since we started so it has already delivered a great benefit to the area.”


If you value what this story gives you, please consider supporting the Islington Gazette. Click the link in the orange box above for details.

Most Read

Become a supporter

This newspaper has been a central part of community life for many years. Our industry faces testing times, which is why we're asking for your support. Every contribution will help us continue to produce local journalism that makes a measurable difference to our community.

Most Read

Latest from the Islington Gazette